07/28/21 Update -Building Leased

Building is now fully leased. Tenant improvement work to start soon.

12/06/20 Update - Scaffolding removed

On track for March 2021 warm shell completion. It is beginning to look like a building. View from Minnesota Avenue, Southern view View...

11/04/20 Update - Plaster, insulation etc

On track for March 2021 warm shell completion. Plastering and insulation in progress. 3rd floor insulation Covered parking area Plastering

10/01/20 Update - Warm shell ready in Q1

We are plastering the exterior and wiring up the interior. Elevator installation next. Plastering the east side of the building View from...

07/16/20 Update - Construction resumed in May

After no construction in March and April due to Covid lockdown, we resumed construction first week of May and have made steady progress...

02/18/20 Update - Pan decks

Steel framing is almost done. Pan decks are being installed.

01/17/20 Update - Asphalt

More rains. But, we were able to lay the first layer of asphalt.

01/10/20 Update - Base rock

Construction process slowed down due to the holidays and rain. Base rock layer was installed around the perimeter of the building and...

12/10/19 Update - Slab pour done.

Slab was poured and then the rain gods gave us a visit. Now graders are prepping site to pour first layer of asphalt. This should give us...