1133 Minnesota Ave, San Jose
Professional Office - Downtown Willow Glen - Fully Leased
07/28/21 Update -Building Leased
Building is now fully leased. Tenant improvement work to start soon.
04/28/21 Update - Warm Shell Ready
We are finally done with warm shell completion.
12/06/20 Update - Scaffolding removed
On track for March 2021 warm shell completion. It is beginning to look like a building. View from Minnesota Avenue, Southern view View...
11/04/20 Update - Plaster, insulation etc
On track for March 2021 warm shell completion. Plastering and insulation in progress. 3rd floor insulation Covered parking area Plastering
10/01/20 Update - Warm shell ready in Q1
We are plastering the exterior and wiring up the interior. Elevator installation next. Plastering the east side of the building View from...
07/16/20 Update - Construction resumed in May
After no construction in March and April due to Covid lockdown, we resumed construction first week of May and have made steady progress...
03/03/20 Update - Concrete floors
Concrete floors on pan decks are in.
02/18/20 Update - Pan decks
Steel framing is almost done. Pan decks are being installed.
01/28/20 Update - Steel Framing
Started steel framing this week.
01/17/20 Update - Asphalt
More rains. But, we were able to lay the first layer of asphalt.
01/10/20 Update - Base rock
Construction process slowed down due to the holidays and rain. Base rock layer was installed around the perimeter of the building and...
12/10/19 Update - Slab pour done.
Slab was poured and then the rain gods gave us a visit. Now graders are prepping site to pour first layer of asphalt. This should give us...
11/15/19 Update - Footings Poured
Footings were poured - slab pour coming soon.
All ready for concrete footing pour the week of 11/03.
#1133minnesota #willowglenofficebuilding